The time allowed for correction or elimination of any cross connection found shall be as follows:
(1) Cross connections which pose an eminent and extreme hazard shall be disconnected immediately and so maintained until necessary protective devices or modifications are made;
(2) Cross connections which do not pose an extreme hazard to the water supply system but nevertheless constitute a cross connection should be corrected within a reasonable period of time. The length of time allowed for correction should be reasonable and may vary depending on the type of device necessary for protection. The water utility shall indicate to each customer, where a cross connection is found to exist, the time period allowed for compliance.
(1993 Code, § 68-74) (Ord. passed 1-22-2001; Ord. 2014-01, passed 1-27-2014)