3-2-14: AWARD OF CONTRACT:
   A.   Lowest Responsible Bidder: The awarding of a contract to the lowest responsible bidder or bidders shall be made within thirty (30) days after the opening of bids unless the city council votes and records the same, for good cause shown, to provide for an extension period. The extension period shall not exceed fifteen (15) days where only state or local funds are involved, or more than ninety (90) days where federal funds are involved. (1985 Code § 7-314)
   B.   Other Than Lowest Bidder: If an award is made to other than the lowest bidder, the city shall accompany its action with a publicized statement setting forth the reason for its action. Such statement shall be placed on file, open to public inspection, and be a matter of public record. (1985 Code § 7-315)