§ 152.25  BREAKER BOXES, CABLES AND FARM POLE LOAD CENTERS.
   Farm pole centers shall be of the meter pole type, 120/240 V three-wire single phase entrance cable. In each building where loads may exist, the service drop shall be on separate breakers from the meter pole. The ampacity of the entrance cable and cable from the load side of the breaks will be calculated in accordance with Tables 310-16 through 310-19 of the most current edition of the National Electric Code or subsequently revised editions. A drawing of a typical farm pole-load center service installation with throwover facilities for emergency generation 400 A, 120/240 V three-wire single phase system may be obtained from the Building Commissioner when an electric permit is obtained for a service installation. A drawing of a farm pole-center service installation 120/240 V three-wire single phase is also on file with, and may be obtained from, the Building Commissioner.
(Prior Code, § 152.15)