(A) Normal connection is a maximum of 1/0 triplex, with a 200-amp meter socket.
(B) Power is to come through a standard secondary.
(C) A customer may have other than the normal overhead connection. The utility will make these connections, but will in all cases require the customer to pay the extra cost over what a normal connection would entail. The excess cost will include both labor and material costs.
(D) On business connections, the customer is to pay one-half the total cost of the project. This cost shall be paid prior to construction.
(Prior Code, § 50.22) (Ord. passed 10-1-1976)