§ 51.121 COMPLIANCE SCHEDULE AND PROGRESS REPORT.
   The following conditions shall apply to any schedule required by this chapter or the town:
   (A)   The schedule shall contain progress increments in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the user or customer to meet the applicable pretreatment standards. (Such events include but are not limited to hiring an engineer, completing preliminary and final plans, executing contracts for major components, commencing and completing construction, and beginning and conducting routine operation);
   (B)   No increment referred to above shall exceed nine months;
   (C)   The user or customer shall submit a progress report to the town no later than 14 days following each date in the schedule and the final date of compliance, including, as a minimum, whether or not it complied with the increment of progress, the reason for any delay, and, if appropriate, the steps being taken by the user or customer to return to the established schedule;
   (D)   In no event shall more than nine months elapse between such progress reports t o the town; and
   (E)   No compliance schedule shall exceed 18 months.
(Ord. 99-04, passed 2-16-99)
Cross-reference:
   Administrative enforcement remedies, see §§ 51.040 et seq.