§ 91.17  PERMIT APPLICATION REQUIREMENTS.
   No permit shall be issued until the public utility shall have applied for a permit to the City Clerk, which application shall provide:
   (A)   Name of street, the surface of which is to be disturbed and the exact location of the proposed street cut on the street;
   (B)   Purpose for which the street cut is to be made;
   (C)   Date on which the street cut activity is to commence;
   (D)   Date on which the surface is to be restored, which shall be no later than 15 days after the date of commencement of activity on the street cut;
   (E)   A good faith estimate of the cost of restoring the surface in accordance with this chapter; and
   (F)   Plan of restoration in accordance with this subchapter.
(1993 Code, § 12.12.020)  (Ord. 98-14-09, passed - -)