10-3-3: TEMPORARY PERMIT; FEE:
Where, for good and sufficient cause, it is necessary to have electricity on any installation before the final certificate can be issued, the electrical inspector may, if all parts to which current is applied are in a safe and satisfactory condition, issue a temporary permit. However, before the temporary permit is issued, the party requesting the permit shall pay to the city the fee as established by motion or resolution of the city council. The permit then received shall be in force for a period of thirty (30) days from its date, and at the end of thirty (30) days, the applicant must reapply, and must reapply each succeeding thirty (30) days thereafter. For each term so requested, the fee shall be as established by motion or resolution of the city council. (1992 Code § 5-404; amd. 2006 Code)