§ 53.12 TEMPORARY SERVICE.
   The city may provide service to temporary construction as follows:
   (A)   The city shall bill for energy used for temporary single phase service for construction of a single family residence or duplex at the residential rate, in addition to the charge for installation and removal.
   (B)   The city shall bill for energy used for temporary single phase and/or three phase service, if available, for construction of apartments, offices, schools, churches, commercial and industrial buildings or similar facilities and to provide energy for fruit stands, fairs, field offices, Christmas tree lots, and the like at the applicable rate schedule in addition to the charge for installation and removal.
   (C)   Contracts covering temporary service in the underground network where overhead service is not available may contain service and cost provisions separate and distinct from other temporary service requirements.
   (D)   Customer's terminal and intermediate support installations for receiving temporary service must maintain N.E.S.C. clearances, be structurally safe and provide an adequate support at the point of the attachment.
(Ord. 440, passed 10-26-2015) Penalty, see § 53.99