§ 152.118.2 MINING STANDARDS.
   Extractive uses are conditional uses and must meet the following standards:
   (A)   Site development and restoration plan. A site development and restoration plan must be developed, approved, and followed over the course of operations. The plan must:
      (1)   Address dust, noise, possible pollutant discharges, hours and duration of operation, and anticipated vegetation and topographic alterations;
      (2)   Identify actions to be taken during operation to mitigate adverse environmental impacts, particularly erosion; and
      (3)   Clearly explain how the site will be rehabilitated after extractive activities end.
   (B)   Setbacks for processing machinery. Processing machinery must meet structure setback standards from ordinary high water levels and from bluffs.
   (C)   Must meet the provisions of M.S. §§ 93.44 through 93.51.
(Ord. 97-2021, passed 7-20-21)