(a) If the work is not completed to the satisfaction of the Street Superintendent, the Village shall either replace or correct the work, applying bond money to cover the expense, or permit the person depositing the bond to do so to the satisfaction of the Village after an additional fifteen day waiting period to determine the suitability of the work done.
(b) If, at the end of the fifteen days, the work is satisfactory to the Street Superintendent, the bond shall be returned.
(c) Any deficiency incurred shall be paid by the person who approved the specifications as provided in Section 905.01(d).
(Ord. 1995-02. Passed 3-13-95.)