§ 13-10-6 REPORTS OF CHANGED CONDITIONS.
   Each user must notify the Pretreatment Coordinator of any planned substantial changes to the user's operations or system which might alter the nature, quality, or volume of its wastewater at least 30 calendar days before the change that results in an increase or addition or planned shutdown or deletion of products. Immediate shutdowns or deletions of products are required to be noticed within five working days of determination.
   (A)   The Pretreatment Coordinator may require the user to submit such information as may be deemed necessary to evaluate the changed condition, including the submission of a wastewater discharge permit application under § 13-8-5.
   (B)   The Pretreatment Coordinator may issue or modify an existing individual or general wastewater discharge permit under §§ 13-9-2 and 13-9-4 in response to changed conditions or anticipated changed conditions.    
   (C)   For purposes of this requirement, substantial changes include, but are not limited to, flow increases of 20% or greater, the addition or deletion of a shift, the discharge of any previously unreported pollutants including changes to the listed or characteristic hazardous wastes for which the user has submitted initial notification under § 13-10-9, introduction of a pollutant for which a monitoring waiver had been obtained, the addition of a new process regardless of waste discharge or lack of discharge, shutdown of a process, or addition or deletion of a product.
   (D)   Significant industrial users and categorical industrial users are required to notify the Pretreatment Coordinator immediately of any changes at its facility affecting the potential for a slug discharge.