1246.21 ACTION BY PLANNING COMMISSION ON CONDITIONAL USES.
   (a)   The Planning Commission shall take one of the following actions:
      (1)   If the proposed conditional use is determined by the Planning Commission to be appropriate and in conformance with the review criteria outlined in Chapter 1290 and Chapter 1272, the Planning Commission shall approve the conditional use. As part of the approval, the Planning Commission may prescribe reasonable requirements on the proposed use to ensure that the development conforms to the intent and purposes of Chapter 1272. The Planning Commission may approve the application for a conditional use without approving the submitted development plan.
      (2)   The Planning Commission shall deny the application if the Planning Commission concludes that, if completed as proposed, the development will not be in compliance with the requirements of this Zoning Code. Such action shall be stated in writing and include specific findings, based upon the evidence submitted, justifying such a conclusion.
   (b)   Failure of the Planning Commission to Act. If the Planning Commission fails to act within sixty (60) days from the date the application was deemed complete, or an extended period as may be agreed upon, then the applicant may deem the development denied.
(Ord. 8-13. Passed 5-14-13.)