1042.04 PERFORMANCE BONDS.
   (a)   A performance bond of 130 percent of the engineer's estimate or contract amount, as approved by the Sanitary Engineer, shall be posted with Council prior to the initiation of construction. A certified check in such amount may be posted in lieu of a performance bond.
   (b)   Release of seventy percent of such bond requires:
      (1)   Completion of main line and lateral construction;
      (2)   Acceptance of the facilities by the Sanitary Engineer after testing is satisfactorily completed and all required repairs are made;
      (3)   Certification of the grade on sewer inverts by a registered surveyor;
      (4)   Recording of all easements; and
      (5)   Completion of all required structures.
   (c)   Release of 100 percent of such bond requires:
      (1)   All manholes, valve boxes and other appurtenances set to grade;
      (2)   Submission of approved "as built" linens or mylars to the Municipality;
      (3)   Posting of a one year maintenance bond equal to ten percent of the construction costs; and
      (4)   Compliance with subsection (b) hereof.
         (Ord. 9-87. Passed 3-9-87.)