1155.20 PLANNING COMMISSION ACTION ON THE FINAL PUD PLAN.
   Within forty-five days of the formal submittal of the final PUD plan, the Planning Commission shall, by motion, make a decision regarding the final PUD plan. In making this decision, the Commission shall, by motion, determine that either:
   (a)   The final PUD plan is in basic conformance with the Preliminary PUD plan and meets the requirements of Section 1155.18 and is approved.
   (b)   The final PUD plan includes major changes from the preliminary PUD plan or otherwise fails to meet the requirements of Section 1155.19 and is disapproved. In its written response to the owner/developer, the Commission shall identify the major changes or other problems in question. The owner/developer may revise the final PUD plan to bring it into conformance with the approved preliminary PUD plan and formally resubmit it for reconsideration by the Commission.
      (Ord. 1992-30. Passed 8-4-92.)