(a) Site plans for development in F-P, R-R, R-1, R-1-A and R-2 districts, exclusive of development subject to Zoning Code, Title One, "Subdivision Regulations", shall be reviewed by the Zoning Inspector.
(b) Site plans for development in R-3, R-4, R-5, B-1, B-2 and I districts shall be referred to the Engineer for review. The Engineer shall report findings to the Planning Commission with a recommendation for acceptance, modification or rejection.
(c) No site plan shall be approved by the Planning Commission or a Zoning Certificate issued by the Zoning Inspector until the site plan meets all requirements of this Zoning Code.
(d) Design of development in R-3, R-4, R-5, B-1, B-2 and I districts shall, where applicable, follow requirements of Zoning Code, Title One, "Subdivision Regulations", as well as any supplemental standards or specifications on file with the Engineer.
(e) Upon approval of a site plan by the Zoning Inspector or Planning Commission, and issuance of a Zoning Certificate by the Zoning Inspector, a developer may commence work.
(f) In the event a developer desires to revise a plan after a Zoning Certificate is issued, and such revision contains changes in the size, location, height of buildings, open spaces, topography, or parking areas, or changes conditions of approval, and such changes require review by the Zoning Inspector, Engineer or Planning Commission, the developer shall apply for a modification of the Zoning Certificate and pay the application fee for a Zoning Certificate.
(g) The Zoning Inspector or Engineer, as necessary, shall conduct field inspections to insure construction in compliance with the approved site plan and Zoning Code requirements.
(Ord. 22-97. Passed 4-1-97.)