9-1-5: SIDEWALKS:
   A.   Required: Sidewalks shall be installed as required by the zoning ordinance, subdivision ordinance or any applicable PUD ordinance. (2013 Code § 11-1-17)
   B.   Specifications: Sidewalks shall be located twelve inches (12") from the street right of way line and shall be constructed in accordance with the following:
      1.   General requirements: All sidewalks shall be constructed of portland cement with twenty eight (28) day compression strength of three thousand (3,000) pounds. Minimum slump shall be three inches (3"). All concrete shall be air entrained. Other admixtures shall be approved by the building and zoning officer.
      2.   Residential districts: Minimum width shall be four feet (4'); minimum thickness shall be four inches (4") with a minimum of four inches (4") of compacted gravel.
      3.   Commercial districts: Minimum width shall be five feet (5'); minimum thickness shall be five inches (5") with a minimum of four inches (4") of compacted gravel. (2013 Code § 11-1-18; amd. 2016 Code)
   C.   Completion Requirements: The public sidewalk provided for in this section shall be completed within six (6) months after the building or structure for which the building permit was issued is completed and occupied. After the expiration of the time limit above, if the sidewalks are not completed, the village may complete or cause the sidewalk to be completed and apply the proceeds of the completion bond, deposit or other security toward the costs thereof, refunding any excess to the party posting the same. (2013 Code § 11-1-19)