Waterway, watercourse, ephemeral stream, and public storm drain protection requirements shall include the following:
(A) If a watercourse will be crossed regularly crossed during construction, a temporary stream crossing shall be installed as approved by the KYDOW and the MS4 representative or their designee.
(B) Stabilization of the watercourse channel shall be made before, during and after any in-channel work.
(C) Stabilization shall be made to adequately prevent erosion at the inlets and outlets of all pipes and paved channels.
(Ord. 14-08, passed 9-3-2014; Am. Ord. 19-02, passed 5-6-2019; Am. Ord. 20-05, passed 7-20-2020) Penalty, see § 54.999