1113.02  SURVEY MONUMENTS.
   (a)   Installation.
      (1)    A complete survey shall be made by a registered engineer or surveyor and all monuments shown in the final plat shall be installed by a registered engineer or surveyor.
      (2)    The traverse of the exterior boundaries of the tract shall close within a limit of error of one foot to 10,000 (.0001).
      (3)   Permanent reference monuments made of stone or concrete with suitable center point shall be located and placed on street intersections within the subdivisions and the cost shall be included in the cost of street improvements. If said monuments have not been set when the plat is accepted there shall be deposited with the Planning Commission, made payable to the City of Campbell a certified check in amount determined by the engineer of the planning, to cover the cost of setting said monuments the amount of which check will be returned after said monuments have been set. Unless said monuments have been set within two years of acceptance of the plat the engineer will cause the monuments to be set with the proceeds of said deposits.
      (4)    There shall be iron pin monuments, three-fourths inch in diameter and thirty inches long, placed at all lot corners and changes in directions by a registered engineer or surveyor prior to sale of any lots within the subdivision.
   (b)    Certification. Installation of required monuments and pins shall be certified by a registered engineer or surveyor. 
(Ord. 62-5165.  Passed 4-24-62.)