(A) Any person connecting to or increasing the flow to the sewerage works shall, prior to being issued a permit to make a connection or modification or to increase the flow, pay a capacity fee as provided herein.
(B) The capacity fee for a residential living unit shall be $420 per living unit. Each unit in multifamily buildings shall be considered a separate living unit for the purpose of calculating the capacity fee. In a trailer park, each existing trailer pad, whether occupied or not shall be considered to be a living unit for the purpose of calculating the capacity-fee.
(C) The capacity fee for commercial, institutional, governmental and industrial accounts shall be determined by the size of the water meter, as follows:
Water Meter Size (in.) Capacity Fee
3/4 $500
1 $750
1-1/2 $1,250
2 $2,500
4 $3,500
(D) In the event the sewer connection provides both residential and commercial service, the commercial capacity fee shall be paid.
(Ord. 741, passed 5-16-94)