§ 112.12 CONSTRUCTION SCHEDULE.
   (A)   On passage of this chapter all work for the installation of the cable television system shall begin immediately and the following schedule maintained.
      (1)   Financing to be secured within 90 days of the passage of this chapter. A certificate to that effect shall be filed by the company with the Clerk-Treasurer within 90 days.
      (2)   Within 90 days of the date of the certificate, the following shall be accomplished.
         (a)   Acquisition of liability insurance as specified herein.
         (b)   Pole contract shall be secured.
         (c)   Make ready requests turned over to telephone and power.
         (d)   Railroad permits filed.
         (e)   Secure lease with the city for headend.
         (f)   Equipment orders placed for cable system and headend.
         (g)   Rent local office spaces.
   All the items listed above except (d) shall be completed by March 15, 1981; and a certificate to that effect shall be filed with the Clerk-Treasurer on or before that date.
      (3)   Final systems walkout to ensure make ready is completed.
      (4)   Cable system construction time shall be six months from the start of construction to 100% completion.
   (B)   In no event shall the above take more than 18 months from the date of the passage of this chapter. Failure to comply with any requirement stated herein shall, upon action of the City Council, make this chapter null and void.
(Ord. 919, passed 8-20-79; Am. Ord. 981, passed 11-17-80)