(A) All service water pipes from the main to the point where the meter is installed shall meet or exceed all state and/or federal guidelines. Such connections shall be wiped joints or brass fittings and one- eighth inch larger than the taps that supply them.
(B) There shall be installed a shut-off valve and curb box at a point six inches inside the line of the sidewalk if such installation is possible; otherwise, said installation shall be on the curb line.
(C) A meter recording the amount of water used and drain cock shall be installed by the applicant, and placed so that they are accessible for service by authorized personnel.
(Prior Code, § 15-3-12)
Statutory reference:
Related provisions, see SDCL § 9-47-1