(A) Prior to final acceptance by the city of the improvements, the engineer for the developer shall submit to the Public Works Director a complete set of drawings of the paving, drainage, water, sanitary sewer, or other improvements, showing all changes made in the plans during construction and containing on each sheet an "as-built" stamp bearing the signature of the engineer and the date. In addition, one reproducible drawing of the utility plan sheets containing the as-built information shall be submitted.
(B) If requested by the developer, field inspection and acceptance can be permitted to allow construction of utilities other than city maintained facilities, prior to final acceptance.
(Ord. 445, passed 12-21-87)