§ 50.25  TOWN ACCEPTANCE OF UTILITIES.
   (A)   When all work is completed and as-built plans are approved by the Utility Superintendent, the developer/owner will be notified that a request can be made for town acceptance of utilities.
   (B)   The developer/owner submits to the Town Council the following information:
      (1)   Engineer’s as-built certification that the work was completed substantially in accordance with the approved plans;
      (2)   Three year letter of credit or maintenance bond for the work in the amount agreed to by the town; and
      (3)   Request for town acceptance of the completed public improvements.
   (C)   Upon acceptance of the public improvements by the Town Council, the developer/owner, lot owner, or contractor may apply for sewer and water permits.
   (D)   The town will not accept utilities until all fees have been paid.
(Ord. 5, 1998, passed 6-10-1998)