(A)
The applicant engineer’s cost estimates for the installation of all required subdivision improvements shall be provided for review and approval by the City Engineer to establish the necessary improvements completion assurance and warranty in an amount required by § 155.141 of this chapter.
(B) When the city accepts an improvement completion assurance for landscaping and infrastructure
improvements for a subdivision in accordance with this section, the city may not deny an applicant a building permit if the subdivision lot meets the requirements for the issuance of a building permit under the Building Code and Fire Code.
(C)
No occupancy may be permitted on any building until all infrastructure improvements have been accepted by the city.
(D) The provisions of this section do not supersede the terms of a valid development agreement, an adopted phasing plan or the state’s Construction Code.
(Prior Code, § 25.07.030) (Ord. 20-03, passed 3-19-2020; Ord. 23-10, passed 4-6-2023; Ord. 24-03, passed 2-1-2024)