§ 152.097 AS-BUILT DRAWINGS.
   At the completion of subdivision construction (and prior to final escrow release under § 152.095(A)(1) of this chapter, or recordation of the final plat under § 152.095(A)(2) of this chapter, as the case may be) the landowner shall deliver to the engineer approved by the town two sets of “as-built” drawings. These drawings shall show all approved changes made during construction and provide physical ties for all water lines, valves, sewer lines, manholes and the like. No escrow funds held by the town, nor final plat withheld pending completion of all conditions and improvements, will be released or recorded until the as-built drawings are received by the town.
(Ord. 49, passed 3-5-2003; Ord. 49A, passed 3-3-2004; Ord. 58, passed 5-8-2008, § 700-3; Ord. passed 7-11-2019)