1147.01 PERMITS.
   (a)   The Zoning Permit shall be issued by the Zoning Inspector.
   (b)   An applicant shall apply for a Zoning Permit with the Village Office Clerk before the construction of a new building or an alteration, addition, or change to an existing structure. The applications shall include the following:
      (1)   Exact dimensions and area of the lot to be built upon;
      (2)   Title, scale, and north point (north shall be at the top);
      (3)   The location, dimensions, and height of the structures to be erected;
      (4)   The location, dimensions, and height of existing structures;
      (5)   The proposed use of all structures;
      (6)   The location of Riparian Setbacks;
      (7)   Illustrate important natural features including, but not limited to, streams, wetlands, ponds, steep slopes and the proposed changes, if any, to existing natural features;
      (8)   The location of oil and gas wells;
      (9)   The location of septic system;
      (10)   The location of water wells;
      (11)   Any other pertinent data as may be necessary to determine and to provide for the enforcement of this Code or any other information required by the Village Engineer.
   (c)   The Zoning Permit shall not be issued to the Applicant until the plans, specifications, and intended use conform in all respects and provisions to this Code. The Village Office Clerk shall keep a careful record of such applications and plans in his office.
   (d)   No Building Permit shall be issued for the construction of a new structure or an alteration or addition to an existing structure unless all the plans, specifications, and intended use conform in all respects and provisions to this Code
   (e)   If construction is not commenced within six (6) months of the date of issuance of the Zoning Permit or construction is not completed within twenty-four (24) months of the date of issuance of the Zoning Permit then the Zoning Permit shall then automatically lapse and be null and void. These time limits may be extended by the Village if the Applicant shows that there has been continuing construction activity on the site during the twenty-four months.
(Ord. 2017-7-15. Passed 9-12-17.)