The fee schedule for application and inspection fees for the office of County Surveyor are as follows:
Subdivision | |
Minor subdivision | |
Primary and secondary | $250 |
Major subdivision | |
Primary | $500 + $15 per lot |
Secondary | $500 + $10 per lot |
Revision – (change to an approved plat not recorded) | $250 |
Amendment – (change to recorded plat) | $250 |
Re-plat – (vacation of a recorded plat) | $250 |
Shopping Center | |
Preliminary Development Plan | $1000 + $15/lot |
Final Development Plan | $1000 + $10/acre |
Amendment to approved Final Development Plan | $1000 + $10/acre |
Planned Unit Development | |
Preliminary Development Plan | $500 + $15/lot |
Final Development Plan | $500 + $10/lot |
Amendment to an approved Planned Unit Development | $500 + $10/lot |
Development Plan Review | |
Preliminary Development Plan | $500 + $15/lot |
Final Development Plan | $500 + $10/acre |
Amendment to Development Plan | $500 + $10/acre |
Commercial/Industrial | |
Application and review | $1,000 + $10/acre |
Individual Residence | |
Regulated drain outlet | $100/outlet |
Regulated drain crossing permit | $150/crossing |
Regulated drain encroachment permit | $150/encroachment |
(Note: All fees in this section of the table can be waived or modified by the County Surveyor and/or the County Drainage Board) | |
Utilities | |
Regulated drain crossing permit | $250/crossing |
Regulated drain encroachment permit | $.25/foot (minimum $250) |
(Note: All fees in this section of the table can be waived or modified by the County Surveyor and/or the County Drainage Board. All fees will be waived if the permit is for work within a new subdivision. A new subdivision refers to a development granted final approval by the County Area Plan Commission within the last 24 months.) | |
Other | |
Removal of obstruction application | $25 |
Variance of regulated drainage easement | $150 |
(Note: All fees in this section of the table can be waived or modified by the County Surveyor and/or the County Drainage Board.) | |
Engineering Review Fees | |
All engineering projects will require a review fee above and beyond the application fees. The review fee shall equate to the contract rate of the reviewing engineer, not to exceed $110/hour. This fee shall be paid to the office of the County Surveyor and shall be paid in full before any project approval is given. | |
Residential | |
Single-family dwelling | $200 |
Two-family dwelling | $250 |
Additions | $50 |
Accessory structures | $50 |
Detached garage | $50 |
Swimming pools | $50 |
Relocation | $50 |
Stop Work Orders | |
Permit re-instatement fee | Minimum $500 or two times the filing fee, whichever is greater |
Continued construction after stop work order | $1,000 first day and up to $500 for each additional day |
Miscellaneous Fees | |
Copy of County Drainage Ordinance | $25 |
Mylar aerial | $1 |
GIS aerial | $2 |
Blueprint copies – 24" x 36" and less | $1.50 |
Blueprint copies – 36" x 48" and larger | $3 |
Returned check fee | $30 |
All fees are non-refundable (unless so permitted by the County Drainage Board) | |
(Ord. 2005-02, passed 2-14-2005)