§ 50.294 INSPECTION BY TOWN OF WORK DONE BY OTHERS.
   (A)   All work on the extension of water or sewer mains not performed by town forces (whether inside or outside the town) shall be subject to inspection by the town, and must be completed in conformance with the town’s specifications and requirements as determined by the Administrator.
   (B)   If, in the judgment of the Administrator, there is a demonstrated lack of competent supervision by a contractor, the Administrator may, at his or her option:
      (1)   Halt work until approved supervision is obtained and the work done in accordance with the town’s specifications and requirements; or
      (2)   Provide constant inspection by town personnel at the expense of the applicant.
   (C)   Inspection of a project by the town does not consist of or imply supervision. The person requesting the extension is solely responsible for ensuring that the project is completed according to town specifications.
(Ord. passed 6-21-2011; Ord. passed 1-15-2019)