8-3-10: TIME TO COMPLETE REPAIRS:
Permanent asphalt repairs shall be completed by the permittee not later than three (3) days after the excavation has been backfilled, unless otherwise authorized by the public works director or his designated representative. If weather conditions prohibit permanent repairs, the public works director, or his designated representative, may authorize the use and installation of temporary cold patches. Such temporary cold patches shall be replaced by the permittee as soon as weather permits. (2003 Code § 8-06-08)