10-8-5: LAND USE TIME LIMITATIONS:
   A.   When a conditional use permit is granted, the land use or construction of its facility proposed in the application must have commenced within three (3) years of the date of the final decision by the commission, or the Board or a court of appropriate jurisdiction, if appealed, and completed within five (5) years of the same date. The following exceptions shall be limited to ten (10) years of the date of the final decision by the commission or the Board or a court of appropriated jurisdiction, if appealed. If the use is not implemented within this time period, the use and its approval shall expire:
      1.   Gravel pits in other than A or A/NR Zones.
      2.   Electrical public service facilities.
      3.   Commercial wind turbines in other than A or A/NR Zones.
   B.   Upon expiration of the use or the approval of that use as provided by this section, the applicant may seek approval of the use only by filing a new initial application for review by the commission. (Ord. 2012-08, 10-9-2012, eff. 10-26-2012)