9-3-3: APPLICABILITY OF CHAPTER:
   A.   Bingham County Zoning Ordinance: Bingham County shall apply Bingham County's zoning ordinance in the area of impact.
   B.   Adoption Of City Subdivision Ordinance: Upon the County receiving an application for a zone change, special use permit, a variance or other applications related to zoning issues within the impact area, the County shall forward a copy of any such application to the City and the City shall have thirty (30) days from the City's receipt of the application to review and respond to any such application in writing to the County. The County shall then proceed with the processing of the application consistent with the County's procedures giving due regard to the City's response, if any.
   C.   Adoption Of City Subdivision Standards: The County agrees to require all new subdivisions (residential, commercial, and industrial) located within one-fourth (1/4) mile of the City of Shelley's City limits or all new subdivisions located outside of one-fourth (1/4) mile of the City of Shelley's City limits if the developer connects to the City's infrastructure to include the following:
      1.   Curb.
      2.   Gutter.
      3.   Five foot (5') Portland type concrete sidewalk.
      4.   City approved street lights - maximum distance three hundred feet (300'), monthly bill to be paid by the City of Shelley.
      5.   Municipal sewer and water, when accessible within three hundred feet (300').
      6.   Reasonable stormwater drainage system.
      7.   Fire hydrants - maximum distance five hundred feet (500') if Municipal system is available.
      8.   Right-of-way for future classification of street (measured from property line to property line) as set forth:
Arterial - Eighty feet (80').
Collector - Sixty two feet (62').
Minor/local- Sixty two feet (62').
      9.   All streets to be constructed to design standards as set forth in Exhibit B (on file in the County and made a part hereof by this reference).
      10.   Stub streets as needed for orderly future development.
      11.   Ten foot (10') utility easement along the front of each property lot.
      12.   All structures must meet minimum setback requirements as set forth:
Residential - (Single-Family Dwelling):
Front property line: Thirty feet (30').
Back property line: Twenty five feet (25').
Side property line/lot line: Ten feet (10').
Side property line/ROW: Twenty five feet (25').
Side street property line: Fifteen feet (15').
Residential - (Two-Family Dwelling):
Front property line: Thirty feet (30').
Back property line: Twenty five feet (25').
Side property line: Eight inches (8") for each foot of building height, but not less than seven and one- half feet (7.5') per side.
Side street property line: Fifteen feet (15').
Residential - (Multiple-Family Dwelling):
Front property line: Twenty feet (20').
Back property line: Twenty feet (20').
Side property line: Eight inches (8") for each foot of building height, but not less than seven and one- half feet (7.5') per side.
Side street property line: Fifteen feet (15').
Commercial:
Front property line: Thirty feet (30').
Back property line: Zero feet (0')/twenty feet (20') if the property abuts a residential zone.
Side property line: Zero feet (0').
Side street property line: Zero feet (0').
Manufacturing/Industrial:
Front property line: Ten feet (10').
Side property line: Zero feet (0').
Side street property line: Zero feet (0').
      13.   Reasonable irrigation system using nonculinary water, i.e. - pressurized irrigation system.
   D.   Subdivision Procedure: The County's application and approval process for the granting of subdivision approval shall apply. Nevertheless, to the extent that the subdivision review process outlined in section 9-3-4 of this chapter differs from the County's application and approval process, the procedures detailed in section 9-3-4 of this chapter shall apply. (Ord. 2006-05, 8-11-2006)