§ 55.56 REQUIRED RELEASE RATE.
   The maximum allowable release rate will be determined by the three-year predevelopment conditions. The predeveloped condition will be taken as the three-year intensity multiplied by the weighted C (as determined for the rational formula) but cannot exceed 0.2 cfs per acre. Calculations supporting the release rate will be submitted along with other calculations required. The Director of Public Services may increase or decrease the allowable release rate based on the current capacity of the City storm sewers.
(Ord. 420-4-97, passed 4-21-97)