Where additional pretreatment, secondary containment, and/or operation and maintenance activities will be required to comply with this chapter, the discharger shall provide a declaration of the shortest schedule by which the discharger will provide such additional pretreatment, secondary containment, and/or implementation of additional operation and maintenance activities.
(A) The schedule shall contain milestone dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment or secondary containment required for the discharger to comply with the requirements of this chapter including, but not limited to, dates relating to hiring an engineer, hiring other appropriate personnel, completing preliminary plans, completing final plans, executing contracts for major components, commencing construction, completing construction, and all other acts necessary to achieve compliance with this chapter.
(B) Under no circumstance shall the POTW permit a time increment for any single step directed toward compliance which exceeds nine months.
(C) Not later than 14 days following each milestone date in the schedule and the final date for compliance, the discharger shall submit a written progress report to the POTW including no less than a statement as to whether or not it complied with the increment of progress represented by that milestone date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and steps being taken by the discharger to return the construction to the approved schedule. In no event shall more than nine months elapse between such progress reports to the POTW.
(Ord. 312-3-92, passed 3-16-92; Am. Ord. 493-05-02, passed 5-20-02)