(A) A construction permit issued by the office of the City Engineer shall be required prior to any construction or installation of improvements to be located within street and alley right-of-way or to be located within utility or drainage easements.
(B) The issuance of the construction permit shall be conditioned upon the following:
(1) Final plat approval by the Council;
(2) Approval by the City Engineer of preliminary plans and specifications for the construction and installation of the improvements;
(3) Submission of a performance bond in a form and amount approved by the City Engineer and City Attorney;
(4) Payment to the city of an inspection fee in an amount as follows:
(a) Two percent of the first $100,000 construction costs;
(b) One and one-half percent of the next $100,000 construction cost; and
(c) One percent of all over $200,000 construction cost.
(5) The date of commencement of the construction shall be approved by the City Engineer.
(Prior Code, § 13-548) (Am. Ord. 1292, passed 6-19-84; Am. Ord. 1974, passed 8-6-19)