§ 53.18 PROCEDURE FOR REMOVAL OF LEAD LINES.
   In the event that a water user desires to have lead service lines replaced, the city Water Department will first verify whether the service has not yet been replaced by digging at the curb shut off and physically examining both sides of the shut off. The user is responsible replacing any lead service lines on the user's side of the shut off, and the city will replace any lead service line between the shut off and the main. If a replacement if deemed necessary, then the user shall replace the user's side, and then upon the city's satisfactory inspection of the user's replacement of the line, the city shall then replace its line between the shut off and the main.