9-2-6: CONNECTION TO SYSTEM:
No connection with a water main shall be made without a permit being issued and twenty four (24) hours' notice given to the superintendent of public works. All connections shall be made under the supervision of the plumbing inspector, and no connection shall be covered until the work has been inspected thereby. Application for permits to make connections must be made to the village clerk, and a fee as established by the village board of trustees shall be paid for each connection. (1976 Code § 13.04.050; amd. 2016 Code)