(A) Any activity disturbing one (1) or more acres of soil is subject to the provisions of this section and shall not take place without an authorized land disturbance permit.
(B) Land disturbance activity less than one (1) acre on individual lot(s) or parcel(s) that are part of a larger common plan of development that disturbs one (1) acre or more of soil, and currently covered by KPDES NOI, is not exempt from this section or Land Disturbance Permit. In this situation, the landowner and/or developer of the larger development, and the individual lot owner(s) or homebuilder(s), will be issued a separate Land Disturbance Permit and will be responsible for complying with the provisions of this section. The landowner and/or developer of the larger development will remain jointly responsible for said lot(s) until such time that the larger common plan of development reaches 80% build-out.
(C) Land Disturbance activity less than one (1) acre on individual lot(s) or parcel(s) that are not part of a larger common plan of development is not exempt from this section or land disturbance permit. The following information is required for submittal of the land disturbance permit:
(1) Land disturbance permit application.
(2) Completed EPSC land disturbance form.
(3) All fees for said permit shall be paid according to the established Permitting Fee Schedule.
(D) The City of Berea may on a project-by-project basis exempt other minor land disturbance activities not specifically identified in the exemptions above.
(Ord. No. 24-14, § 1, 12-16-14)