§ 71.203 VALUATIONS TO BE FAIRLY ESTIMATED
   If, in the opinion of the building official, the valuation of a building, alteration, or structure appears to be underestimated on the application; the permit shall be denied, unless the applicant can show detailed estimated cost to meet the approval of the building official. Permit valuations shall include total cost such as plumbing, electrical, mechanical equipment, and other systems.
(Ord. No. 3.72, § 5, 3-21-72)