§ 110.05 DEMOLITION PERMIT.
   (A)   Application. Application by any person for a demolition permit shall be filed with the Village Administrator. The application shall describe the demolition to be accomplished and shall designate the manner, method, and equipment to be used. Application shall be made by the owner or the contractor employed to conduct the demolition, or the agent of either; unless made by the owner, the applicant shall evidence his or her authority to make application by means of a duly verified affidavit of the owner. The application shall indicate the date upon which demolition is intended to begin and the probable date of completion thereof.
   (B)   Issuance of permit. Prior to issuance of the permit the Village Administrator shall determine that the proposed method of demolition is in accordance with good engineering practices and that the contractor or owner has the necessary and proper means and equipment to accomplish the demolition in accordance with the manner, method, and equipment specified in the application.
   (C)   Fees. The fees for a demolition permit shall be at the rate of $20 per structure for a four-day period. Beyond the four-day period there shall be an additional charge of $10 for each day until the final inspection certificate can be issued.
(Ord. 34-04, passed 5-17-2004)