§ 90.34 MATERIAL TO BE USED.
   Material satisfactory to the Village Street Superintendent shall be used as the final course so there will be a firm and solid surface. In no case shall the material so placed be allowed to project above or below the grade of the road as originally established. All surplus material shall be removed in a manner satisfactory to the Village Street Superintendent. The permit holder shall maintain the pavement and berm over the trench in a manner acceptable to the Village Street Superintendent. The surface and base of the disturbed pavement shall be replaced with the material specified by the Village Street Superintendent and according to his specifications. The area of pavement to be replaced shall extend 12 inches outside the limits of the ditch in all directions. The pavement will be replaced with eight inches of concrete and overlaid with four inches of asphalt ODOT 404 if the existing pavement is asphalt.
(Ord. 25-2015, passed 9-1-2015) Penalty, see § 90.99