§ 161.036 PERMIT TO BEGIN GRADING AND CONSTRUCTION.
   (A)   Permit approval. The City Engineer must approve a permit to begin grading and construction. Such application for permit shall be made by the developer to the Engineering Department on the application to install improvements, available in the City Engineer’s office. Such application may be approved by the City Engineer only after the improvement plans are approved by City Council. Further, the application will be approved only after the proper form of assurance is accepted by the city. (See §§ 161.066 and 161.067 of this chapter.)
   (B)   Permit display. The approved application to install improvements must be prominently displayed at the entrance to the subdivision until all improvements are accepted by the city. In the case that a subdivision has multiple entrances, copies of the application must be prominently displayed at each entrance.
(1960 Code, § 41-3-2) (Ord. 7128, passed 4-28-2008)