1109.04 CONSTRUCTION REQUIREMENTS.
   (a)   Cooperation of Subdivider and/or Contractor. The subdivider and/or contractor shall have available on the project at all times, a clearly reliable copy of all required plans and specifications. He shall cooperate with the Inspector and with other contractors in every way possible. The subdivider and/or contractor shall at all times have a competent representative acting as his agent on the project. The representative shall be capable of reading and thoroughly understanding the plans and specifications and he shall receive instructions from the Inspector. The representative shall have full authority to execute the orders or directions of the Inspector. The representative shall have full authority to execute the order or directions of the Inspector and to promptly supply such materials, tools, plant equipment and labor as may be required. The Inspector's orders should be executed without delay. A representative shall be furnished irrespective of the amount of work sublet.
   (b)   Grade Stakes. Pavement and pipe grade stakes shall be set at twenty-five foot intervals. The Inspector may ask for additional grade stakes if it is deemed necessary. Other means of line and grade may be used as approved by the City Engineer.
   (c)   Repair or Damage. Any damage done to the improvements by construction traffic, local traffic or by any other means shall be repaired or the damaged materials replaced in a satisfactory condition.
   (d)   Erosion Control. The subdivider and/or contractor shall take necessary procedures to prevent erosion and downwash of grits and sediments into adjoining properties or existing drainage facilities. No project will be released from bond from failure to comply with this regulation without cleanup and repair of damages. The City Engineer may request stoppage of work during construction if he deems it necessary to protect outside facilities, but failure to do so may not relieve owner of downstream liabilities. Final inspection requires all drainage facilities free from depositions of erosion or construction debris.
   (e)   Final Cleaning Up. Upon completion of the work and before acceptance, the subdivider and/or contractor shall clean all ground occupied or affected by him in connection with the work. The entire area shall be left in a neat and presentable condition.
   (f)   Maintenance of Improvements. The subdivider shall be responsible for the maintenance of the improvements installed and shall be responsible for providing the services necessary to guarantee access to all the occupied lots, including snow removal, until final acceptance upon recommendation by the City Engineer. The performance of such work shall be guaranteed by a maintenance bond, the amount of which shall be determined by the City Engineer and approved by the Planning Commission. The subdivider shall maintain all improvements for such periods as specified in the construction agreement, or by the City Engineer.