10-6-14: BUILDING PERMITS REQUIRED:
   A.   Permits Required: No buildings or other structures shall be erected, moved, added to, or structurally altered, and no land use shall be established or changed in use, within city limits or property outside the city limits within the extraterritorial limits of this title, without a permit therefore, issued by the Community Development Department.
   B.   Building Permits Approval: Within ninety (90) days after the receipt of a complete application, the Building Official shall either approve, conditionally approve or disapprove the application. Work shall commence within one hundred eighty (180) days of the issuance of a building permit. (Ord. 2023-7, 7-17-2023)