The grantee will proceed as follows pursuant to Federal Communications Commission's regulations:
(A) Apply for all necessary grants or waivers within 90 days of issuance of franchise.
(B) Apply for pole attachment agreements with the appropriate companies within 30 days after issuance of franchise.
(C) Submit to the city detailed system layout plans within six months after obtaining necessary pole attachment agreements.
(D) Begin construction within 30 days after written approval by the city on system layout plans and receipt of a certificate of compliance from the Federal Communications Commission (FCC).
(E) Render service to customers in the first section no later than six months after commencement of construction, as defined in division (D) above.
(F) Render service to all feasible areas within the city within 24 months after commencement of construction, as defined in division (D) above.
(Ord. 2-1976, passed 8-2-76; Am. Ord. 3-1993, passed 4-19-93)