§ 151.059 AUTHORIZATION TO CONSTRUCT AND TERM OF VALIDITY.
   The township’s approval of an SWM site plan authorizes the installation/construction of the regulated activities described in the approved SWM site plan for five years following the date of approval (term of validly). The township may specify a term of validity shorter than five years in the approval for any specific SWM site plan. Terms of validity shall commence on the date the township issues the approval for an SWM site plan. If an approved SWM site plan is not completed according to § 151.055 within the term of validity, then the township may consider the SWM site plan abandoned and may revoke any and all permits issued under or in conjunction with the plan’s approval. SWM site plans that are considered abandoned by the township shall be resubmitted in accordance with § 151.057 of this chapter.
(Ord. 239, passed 10-14-2020)