Subject | Fees
|
Subject | Fees
|
Floodplain building permit | |
Estimated costs | |
$0 to $500 | $0 |
$500 and up | $5 |
Licenses, permits, and general business regulations | |
Event permit/license\ | |
Each transient retail vendor during an event | $10 per day |
Event sponsor | No fee |
Temporary food sales permit | |
Per week or part thereof | $150 |
Per month or part thereof | $300 |
Per year or part thereof | $450 |
Transient retail business permit | |
Per week or part thereof | $300 |
Per month or part thereof | $600 |
Per year or part thereof | $750 |
Yard sale permit | $0 |
Storage of building materials or placement of dumpsters | |
Permit fees for storage of building materials or placement of dumpsters on the street and/or sidewalk by initial issuance or extension are hereby established as follows: | |
1-7 days | $25 |
Over 7 days | $5 per day |
Any permit issued for the same location within 30 days of a prior permit shall be deemed to be a continuation of the prior permit for the purpose of calculating the permit fee. | |
Sign | |
Off-lot directional sign | $10 |
Permit | $10 |
Street and sidewalk | |
Excavations | |
Issuance fee | $30 |
Six-month extension | $10 |
Subdivision | |
Minor subdivision | |
Preliminary plan/final plan (a combined submission) | $50 |
Professional review fee | Based on actual cost incurred |
Major subdivision | |
Preliminary plan | $150 + $10 per lot |
Professional review fee | Based on actual cost incurred |
Zoning | |
Certificate of nonconformance | $50 |
Change or amendment in zoning ordinance or map | $400 |
Statement of classification or compliance | $25 |
Zoning Hearing Board certificate | $200 |
Zoning permit | $25 per first $1,000 in construction costs and $1 per each additional $1,000 in construction costs |
Zoning permit (temporary) | $25 |
(Res. 09-2012, passed 7-2-2012; Res. 2019-02, passed 3-4-2019; Res. 2021-01, passed 7-6-2021)