§ 8-1-28 IMPROVEMENTS REQUIRED; COMPLETION.
   (A)   The subdivider shall install and construct all improvements required by this chapter. All required improvements shall be installed and constructed in accordance with the specifications and under the supervision of the City Council and to its satisfaction.
      (1)   Streets and alleys. All streets and alleys within the platted area which are dedicated for public use shall be brought to the grade approved by the City Council.
      (2)   Roadways. All roadways shall be surfaced with portland cement concrete. This shall be for all streets to be approved by the City Council.
      (3)   Sidewalks. Sidewalks may be required by the City Council if they are considered necessary for the general welfare and safety of the community. Sidewalks shall be constructed to the grade approved by the City Council.
      (4)   Water lines. Where a public water main is reasonably accessible, the subdivider shall connect with such water main and provide a water connection for each lot with service pipe installed to the property line in accordance with the City Water Department standards, procedures and supervision.
      (5)   Sewers. Where a public sanitary sewer is reasonably accessible, the subdivider shall connect or provide for the connection with such sanitary sewer and shall provide within the subdivision the sanitory sewer system and required to make the sewer accessible to each lot in the subdivision. Sanitary sewers shall be stubbed into each lot. Sewer systems shall be approved by City Council.
(Prior Code, Art. 4, Ch. 1, § 15)
   (B)   Before the City Council will approve the final plat, all of the foregoing shall be constructed and accepted by formal resolution of the City Council.
(Prior Code, Art. 4, Ch. 1, § 16)
(Ord. passed 4-2-1985)