18.04.090: INSPECTION REQUIREMENTS:
Within thirty (30) days after a facility becomes operational, and each year thereafter, the facility operator shall conduct a safety inspection in accordance with FCC standards and within sixty (60) days of the inspection, file a report with the village. However, at the option of the village, the village may secure the services of an independent safety consultant to conduct a safety inspection, and the owner of the facilities shall reimburse the village for the reasonable cost of said inspection. In addition, the facility operator shall provide the village, on a quarterly basis, a report stating the active or inactive status of the facilities including the tower and antennas. Additionally, in the event there are any increases to the wattage of the tower output, the facility operator shall notify the village within five (5) business days of any such wattage increase. (Ord. 1997-O-26)