15.08.090: EXPIRATION, RENEWAL OF PERMITS:
   A.   No permit issued under this chapter or any ordinance requiring a permit for the construction, addition or alteration of any building or structure shall authorize any work later than one year from the date of the issuance of the permit.
   B.   Any permit issued under this chapter may be renewed for a period of six (6) months by application being made therefor within the one year period of the original permit and the payment of an application fee as provided in the fee schedule of the village, as amended.
   C.   In the event the proposed improvement for which the initial building permit and the six month extension of the renewal permit has not been completed, a new permit must be applied for and fees required by this section for the original permit must be paid.
   D.   No permit shall be renewed to a person who has failed to pay any fine, penalty or debt owing to the Village (“Village Debt”). A person whose permit renewal application is rejected based on a Village Debt may appeal the decision, which appeal must be in writing and filed with the Village Clerk within ten (10) days following the decision. The written appeal must include the basis for contesting the Village Debt and other information that will help the applicant’s case. Within the body of the written appeal, the Applicant may also request a hearing to contest the Village Debt. The Village Administrator will set a hearing date within ten (10) days of the receipt of the written request for hearing and will rule on any appeals that are timely filed. If a timely written appeal is not filed, the Village Debt will be considered final. (Ord 2019-O-24 § 21: Ord. 2014-O-36: Ord. 1998-O-02 § 1)