10-7-5: INTERIM USES:
   A.   Purpose And Intent: An interim use permit is intended to serve those uses that are specific to a particular property or that may only be reasonable for a limited duration due to the type of activity or the changing character of the neighborhood.
   B.   Power To Issue: The city council, after a recommendation from the planning and zoning commission, may grant an interim use permit if the use conforms to all applicable zoning ordinances, the date or event that will terminate the use can be identified with certainty and the applicant agrees in writing to any conditions that the city deems appropriate regarding the use and its termination.
   C.   Procedures And Information Requirements: Interim use permits shall be processed according to the standards and procedures for a conditional use permit as established by section 10-7-4 of this chapter.
   D.   Evaluation Criteria: An interim use shall comply with the following:
      1.   Meet the standards of a conditional use permit set forth in section 10-7-4 of this chapter.
      2.   The use is allowed as an interim use in the respective zoning district.
      3.   The date or event that will terminate the use can be identified with certainty.
      4.   The use will not impose additional unreasonable costs on the public.
      5.   The user agrees to any conditions that the city council deems appropriate for permission of the use.
   E.   Termination: An interim use will be terminated by:
      1.   The date stated in the permit.
      2.   Upon violation of the conditions under which the permit was issued.
      3.   Upon change in the city's zoning regulations which renders the use nonconforming.
      4.   The redevelopment of the use and property upon which it is located, to a permitted or conditional use as allowed within the respective zoning district. (Ord. 2014-24, 10-21-2014)